Newsletter #29, September 2011

bolting pit rails together

We've made good progress with the inspection pits in the rail vehicle shed in recent times, as can be seen in this image, Steve, Ben and Ray bolting up a freshly installed running rail on the road 2 pit on 14 August 2011. In the background Tr189 can be made out, complete with black and yellow stripes on headstocks. Photo: Hugh McCracken.

In this issue:

Mainline track | Shunting locomotive | Rail vehicle shed | Chairpersons Inclinations: Maymorn Structure Plan | Upcoming events | Snow

Mainline track

Our mainline track has received a little more attention over the winter months after ballast delivery in March. Two further lengths of 50kg rail have been laid, sleepers installed, some of which required a lot of ballast to be shifted first! Further extension of our mainline track is pending excavation and widening of our entrance road, although we may do a little more work at the pedestrain crossing in the meantime.

Further work is also planned on our doubleslip through spring, with key equipment including rail drill, rail saw and crow up and running.

mainline under construction near pedestrian crossing

Some of the mainline track just tackled included an awkard situation of our own making with ballast piles located a little close. At press we've built through and past this spot!

mainline at Maymorn under snow

In mid-August the whole country seemingly received a dumping of snow, and Maymorn was no exception! This was the scene on Wednesday 17 August - which would have been considerably more impressive a day earlier (roads were closed, however).

Shunting locomotive

Ron painting stripes onto headstock of Tr189

Ron putting the finishing touches on bumblebee stripes on headstocks of Tr189 on 30 April 2011.

Work has continued on our shunting locomotive Tr189 over the winter months. The whole exterior of the locomotive has been painted, including the outside of the frames and wheels. We have also just removed the protective corrugated iron from the windows as the rail vehicle shed is now closed in.

We will now turn our attention to mechanical work to get the loco running again, which includes reinstating a number of key appliances. An air compressor has been sourced and has been worked on behind the scenes. A mechanical assessment has been completed, and we have a fair idea of the scope and extent of the work to be done. We hope to be able to drive the loco out of the shed in Autumn 2012.

Rail vehicle shed

Workshop

Work has continued on the workshop extension to the rail vehicle shed inbetween work on the train and pedestrian doors. Four portal pods have now been poured, and work has started on the intermediate foundation wall sections. A huge amount of backfilling is required, but in the interim we plan to level out the foundation area with compacted fill. This will enable concrete trucks to access the wall sections and make the area safe for cherrypicker and other access equipment.

workshop foundations with four portal pods and wall subfoundations under way

Workshop foundation progress in this mid-August view we were working on subfoundations for each of the walls that span between the portal pods. Given a few more days work this view will transform significantly.

Train doors

lifting train door frames into position, Masterton end of shed

After fitting hinge gudgeons to the train door frames during March and April we installed the bi-folding door frames. Clive Davis did the honours with his hiab truck, the whole process going remarkably smoothly.

Lionel painting door frames

Lionel painting train door frames in preparation for cladding at Upper Hutt end of the rail vehicle shed, 23 April 2011.

sanding train door frames

Bart, Glenn and Ron sanding and preparing door frames for painting at the Masterton end of the rail vehicle shed.

Upper Hutt end of shed with closed-in train doors

A late-afternoon shot of closed-in train doors at the Upper Hutt end of the rail vehicle shed on 13 August 2011. Just the pedestrian doors to complete…

Ron and Lionel working on a pedestrian door

Ron and Lionel working on the second of three pedestrian doors donated by Maymorn Joiners Limited.

Closed in

A long-awaited milestone for our rail vehicle shed project! During August we fitted three stout wooden pedestrian doors to the shed door frames. Quite a few details to work through, including use of parliament hinges, fire escape mechanisms and water-tightness. On 27 August Lionel completed fitting the last door and we now have a closed-in shed.

Inspection pit coming together

During the winter months of 2011 we continued work on the road 2 inspection pit inside the rail vehicle shed. During 2010 we installed steel pit columns onto concrete floor beams, laid rail over a 16 metre length, and brought the second of seven carriages inside under cover. Rails will continue over the remainder of the steel columns, then land on a short length of concrete pit. The remainder of road 2 will be laid in tracksets so that we can bring additional carriages in under cover, and start to use the facility for inspecting and maintaining rail vehicles.

Approximately 16 metres of floor foundation between the two roads has been prepared, reinforcing laid and inspected and is ready for concrete to be poured. A further grant application has been lodged for funds towards additional reinforcing steel and concrete to progress this work.

concrete pit at night

Here we see progress with a 2.4m length of between-rails concrete pit, not long after formwork had been removed, on 3 August 2011.

John tends to concrete patching work

The short concrete section of inspection pit seen on 14 August, shortly before rails were rolled into position. Canted n-plates have been grouted into place over studs cast into the concrete.

AL2044 located on new section of inspection pit

On 13 August 2011 we moved AL2044 along the inspection pit road, having installed the far set of rails earlier in the day. The floor area between the two pit roads is ready waiting for concrete - and funding! Photo: Hugh McCracken.

Chairpersons Inclinations: Maymorn Structure Plan

We felt it was important to make a submission to the Maymorn Structure Plan. Following is a summary of our submission. The Trust made a submission to the structure plan. The plan has the potential to make a direct impact on the Trust's Maymorn site and the connection route from there to the heritage formation near Tunnel Gully.

The structure plan proposes a multi-stage urban development for the Maymorn area, with a railway corridor for the Rimutaka Incline Railway climbing out of Maymorn station. We recommended that additional integration and connections be put in place so that the railway passes through a "railway reserve", highlighted and made prominent in the urban landscape - and so that visitors might be able to view the heritage railway operations first-hand from adjacent cycleways, paths and carriageways.

The railway reserve and associated walk and cycleway will enable additional connecting routes to be formed between the hub of the community - the railway station - the GWRC Park land leading into Tunnel Gully, and the walkway proposed to be located along the historic railway route leading towards Mangaroa. This will reinforce and promote use of the existing Tranz Metro service for cycle and walking recreational activities to and from Maymorn station. Additionally, the Trust has incorporated a cycleway / walkway into its wider proposal for a heritage railway along the historic railway route to Kaitoke and Summit. Provided an adjacent cycle / path in the railway reserve will maintain the nature of the route as it passes through the Maymorn urban area. There will also be a significant public good in having the heritage railway operations viewable from the adjacent cycle / path.

We have already undertaken extensive design work for the route, utilising available landforms between Maymorn and the historic railway formation as it passes into Greater Wellington Regional Council land near Tunnel Gully. There is, however, little room for adjustment in the alignment, as it is up against minimum curvature (100m radius) and maximum gradient (1 in 35) for all but the initial stretch out of the station.

In the next few weeks the Trust will attend hearings associated with submissions to the structure plan, and speak in support of our own submission. We hope to continue discussions with the Council and work towards formalising the railway alignment as a railway reserve.

proposed low flank route community integration

Proposed alignment of connection route climbing out of Maymorn, showing possible integration into a network of cycle / pathways, connecting into a walkway along the heritage railway formation that heads to the south up the Mangaroa Valley, and both railway and walkway connecting into Tunnel Gully. Drawing: Ben Calcott.

proposed railway reserve community integration

An impression of how the railway reserve could look in elevation — with reserve, cycle / path, berm and carriageway elements. Drawing: Ben Calcott.

Upcoming events

Snow

English Electric unit in snow at Waterloo

A rare sight - With snow covering the cabbage trees on the right, an English English service makes its way north out of Waterloo station at 4:58pm, Tuesday 16 August 2011.

Contacts

Full contact details may be had on the Trust’s website at www.rimutaka-incline-railway.org.nz/contacts.html,

Electronic copy

An electronic copy of this newsletter will be available on the Trust’s website at www.rimutaka-incline-railway.org.nz/member-pages/newsletter-29.html from 12 September 2011. Further copies can be printed, or images viewed in colour (where applicable). Photos by Hugh McCracken unless otherwise stated.