Newsletter #18, February 2007

Track laid with concrete sleepers towards rail vehicle shed site.

Recent progress at the Maymorn site has seen track laid with concrete sleepers, including a number from the “sponsor a length of track” campaign. The track extends either side of the trackset laid on the Trust’s official launch on 29 October 2005. In this view taken on 17 February 2007, the track leads to the site of our future rail vehicle shed. Details and images of recent track work are included in the Sponsor a length of track! story in this issue. Photo: Hugh McCracken.

In this issue:

Resource Consent.

The Chairperson’s inclinations.

Sponsor a length of track.

Want to see some track at Maymorn? Here's your opportunity to help us get started.

Wagons Roll!.

Pakuratahi deviation investigation with MWH.

Maymorn progress:

- Construction of Pedestrian Crossing.

- New Zealand Community Trust grant for fence.

Summit tree planting.

Looking back…

Wb 299 on shed at Westport.

Engine sheds and Baldwin locos — the best of both worlds!

Upcoming events | Contacts | Electronic Copy

The Chairperson’s inclinations

Resource Consent

As mentioned in the lead story, a huge amount of work has gone into resource consent application and associated assessment of environmental effects. Consultation with potentially affected parties is time-consuming — but it is important to involve the community at the early planning stages of any large project. As this newsletter goes ‘goes to press’ we anticipate that the resource consent application will be a matter of days from being lodged with Upper Hutt City Council, and that it will be fully notified. A decision should be had by late Autumn.

Rail vehicle shed in brief

Design work is being finalised, and the plans are currently with engineers for validation. The final length of shed, and extent of involvement of contractors is pending a decision in March on a funding application submitted to the Lotteries Grants Board Environment and Heritage Committee.

Hugh McCracken installing first concrete sleeper.

The first length of sponsored track being installed just past the 0km peg at Maymorn on 9 December 2006. Photo: Hugh McCracken.

Sponsor a length of track

The ‘Sponsor a length of track’ campaign is underway, with a number of people taking the opportunity to have a permanent record of their support in our ‘permanent way’.

Good progress has been made, with four packs of sleepers, 96 in total, delivered from Stresscrete’s Hamilton concrete sleeper batching plant to Wellington in December. On 9 December the first sponsored sleeper was installed in the Maymorn yard, as seen in the accompanying image.

Elsewhere in this newsletter, and on our web site, you will find details on the sponsorship options, which give opportunities at entry, medium and high ends of the range. Automatic payment options are also available, which we hope will bring the sponsorship packages within reach of most people.

Maymorn project

Work programme for Autumn will include:

Ballast wagons

As outlined in our previous two newsletters, Ontrack have been most generous in making surplus wagons available at scrap rates, which means that a 7–tonne ‘Yc’ or ‘Yf’ wagon will cost approximately $2,000 including transport to the Maymorn site. We figure that a train of wagons will be required to relay an 18km railway, rather than just a handful — and this is the opportunity to secure what is needed for the future.

YC2243 on a Midland Line work train

YC2243 on a Midland Line work train on 15 December 2005. Ballast is being off-loaded from side-dumping YD-class bogie wagons ahead of maintenance work in the area, whereas the YC is yet to discharge its load. As at 13 February 2007 YC2243 was still in service, 1 of 28 wagons of its class located at Greymouth. Photo: Adam Orchard.

ballast train on the Midland Line.

The same train as the previous photo on the move to another work site to discharge ballast. The Trust will require a similar train to build an 18km long railway. Photo: Adam Orchard.

As at 21 February 2007, 26 of the 40 new “YJ” bogie ballast wagons had been released to traffic from Hillside Workshops, including:

Now there is a rake of new wagons in the North Island it is likely that a start will be made on decommissioning the old “4-wheelers”.

The Trust needs your help to secure a dozen ballast wagons — opportunity to purchase the decommissioned wagons is approaching fast. Sponsorship of individual wagons would be a most welcome gesture and we would happily entertain naming rights, logos or other signs put on wagons to acknowledge your support. Please contact the Trust if you can help sponsor a wagon: enquiries@rimutaka-incline-railway.org.nz or telephone 021 701 551 — we would be glad to hear from you.

Pakuratahi deviation investigation with MWH

Silvia Allan, Keith Robertson and Keith Woolley, 2km from Summit.

Silvia Allan and Keith Robertson, MWH consultants and Keith Woolley of Greater Wellington Regional Council stop to view a potential rail bridge site over the Pakuratahi River, 2km from Summit. Photo: Hugh McCracken.

On 26 October 2006 Trust Chairperson Hugh McCracken accompanied MWH Global consulting engineers and a Greater Wellington Regional Council officer on a half-day exploratory trip up the Pakuratahi valley. A high dam at Ladle Bend on the Pakuratahi River is one of three sites being evaluated to cater for Wellington’s future water requirements, the others being Skull Gully, in the Orongorongo catchment, Wainuiomata, and the Whakatiki site, Belmont Regional Park.

The Trust has acknowledged the necessity to provide for future water requirements of the region, this being the prime reason for Greater Wellington Regional Council holding the land in the Pakuratahi Forest Park. We have expressed opposition to locating the dam at Ladle Bend, as it would inundate approximately 1.5km of railway formation, and necessitate removal of the historically important Ladle Bend railway bridge. However, the Trust has suggested an alternative to the Ladle Bend location, being immediately upstream of the Summit Stream confluence. This location is being examined as a potential candidate.

Implications for the Trust of the Ladle Bend reservoir site have been considered further, to determine firstly whether a deviation route is feasible, and secondly, to determine likely order of magnitude of cost. The excursion on 26 October explored a possible route that would deviate from the heritage railway formation approximately 2km downstream of the Pakuratahi Tunnel, climb at a gradient no greater than 1 in 40 with minimum 100-metre radius curvature to crest above the dam site, skirt above the shore of the reservoir, finally crossing the head of the reservoir to rejoin the heritage formation approximately 2km from Summit.

Whilst this would be an enormous undertaking for the Trust (more than $15M at commercial rates), and not its first preference, the deviation would be of similar character to other portions of the route. It would, unfortunately, result in loss or deviation away from key heritage railway structures, including the Pakuratahi Tunnel, Pakuratahi Truss bridge and Ladle Bend bridge and 4km of formation that passes through a particularly scenic gorge.

Maymorn Progress

Pedestrian crossing

The pedestrian crossing is almost complete, with major concrete work being done in December 2006.

drainage works 28 October 2006.

Work continued on the pedestrian crossing through Spring 2006, including the installation of field drains and sumps. On 28 October 2006 Ian Shore and Colin Craddock take a well-earned rest from construction work. Photo: Hugh McCracken.

Team place concrete for pedestrian crossing.

On 16 December 2006 saw seven trust members placing Firth ready-mix concrete at the pedestrian crossing. This completed the walking surface on the Parkes Line Road side. Photo: Glenn Fitzgerald.

Peter Milburn, Steve Porter, Hugh McCracken, Wayne Longstaff, John de Graaff.

Peter Milburn, Steve Porter, Hugh McCracken, Wayne Longstaff, John de Graaff and Ian Shore pause for a photograph after placing concrete on 16 December. Photo: Glenn Fitzgerald.

track in position at crossing for future loop.

Over the summer break a short length of track was put in position at the pedestrian crossing, on the future loop alignment. The track still requires ballast and a lift to the design rail height. Once at position boarding will be fitted to give a flat walking surface across the track.

It will be a relatively simple matter at a later date to replace these rails and incorporate the pedestrian crossing into the rail system proper. Photo: Hugh McCracken.

New Zealand Community Trust

New Zealand Community Trust grant for fence

The Trust is grateful for a $4,000 donation from the New Zealand Community Trust, which will be spent on further security fencing materials for the Maymorn site. The Trust intends to fence the site boundary as soon as is practicable. This will enhance public health and safety by precluding entry into potentially hazardous areas, and help protect assets from theft and vandalism.

The fence-building programme is now scheduled to start on the last weekend of Summer, and will continue on through the Autumn months.

NZCT fence

Glenn Fitzgerald, Hugh McCracken and Ian Shore with first post installed on the NZCT-sponsored fence line on Saturday 14 October 2006. This was accurately positioned at 38.457km in order to mark the eastern (Wairarapa) end of the rail vehicle shed. It will be used for location purposes and will carry a datum to establish rail level and floor level for the shed. Photo: Colin Craddock.

Summit tree planting

Sunday 29 October 2006 saw a dedicated number travel to Summit to plant trees and tend to those planted in previous years. The planting session had been postponed a couple of times due to inclement weather, and the weather that day could have been a little better! However, the planting could not be put off any longer as Summer was fast approaching, and a little rain would be good for the trees.

The previous plantings are starting to show good results. Many of the larger flax bushes and other trees are probably going to have some flowers next year, which should improve the bird life there in time.

In 2007 Maymorn will probably have a planting day, first steps of our landscaping work for the site.

Tree planting at Summit.

Members of Forest and Bird and the Rimutaka Incline Railway Heritage Trust battling wind and rain to plant trees at Summit. Photo: Glenn Fitzgerald.

Tree planting at Summit.

Overview of tree planting area at Summit, looking towards the station yard site and Rochfort’s Pass in the distance. Photo: Glenn Fitzgerald.

Upcoming events

Members’ evening: Ballast wagons — Wednesday 18 April 2007, 7:30pm.

The decommissioning of old ballast wagons from mainline service this year marks the end of an era for 4-wheel wagons. A chance to look back at 4-wheel wagons, their successors and our plans to purchase up to 12 wagons for the Rimutaka Incline Railway.

Meet at Level 1 Meeting Room, Upper Hutt City Council, 838–842 Fergusson Drive, Upper Hutt. Access is from the car park to rear of the Council building, 100m east of H2OExtreme. Light refreshments will be provided.

Looking back…

Baldwin Wb 299 at Westport shed, 1950’s.

Baldwin steam 2-6-2T tank engine Wb 299 outside the Westport engine sheds in the mid 1950’s. Twelve of these delightful locos, numbered 290 – 301 were built by Baldwin Locomotive Works, Philadelphia, USA in 1898 for service in New Zealand. Numbers 297 and 298 were initially allocated to Wellington, operating trains on the government line through the Hutt Valley to Upper Hutt and Summit, but were transferred after only a couple of years service to Whangarei and Westport respectively. 298 worked alongside number 299, illustrated above, also numbers 291, 292, 294 and 300, primarily hauling coal trains between inland coal mines and the wharves at Westport.

Two of the Wb class, numbers 292 and 299, were unceremoniously dumped as riverbank protection alongside the Seddonville line, between Seddonville and Mokihinui Mine after more than 50 years service. Trust Chairperson Hugh McCracken was instrumental in salvaging the two engines from Seddonville in 1989, and they currently reside at the Steam Incorporated site, Paekakariki. A return to steam is a distant prospect — but at some time in the future a scene such as that illustrated above may be replicated at Maymorn, with 299 pausing between duties at the engine shed…

Photo: M.W. Adams.

Contacts

Full contact details may be had on the Trust’s website at www.rimutaka-incline-railway.org.nz/contacts.html

Electronic copy

An electronic copy of this newsletter will be available on the Trust’s website at www.rimutaka-incline-railway.org.nz/member-pages/newsletter-18.html from 18 March 2007. Further copies can be printed, or images viewed in colour (where applicable).

The views and opinions expressed in this newsletter are not necessarily those of the Rimutaka Incline Railway Heritage Trust.

Grateful thanks to Jean McCracken and Tim McKenzie for editorial assistance.

13 March 2007.