How will the line be constructed?
21
In broad terms, it is envisaged that the portions of route requiring major earthworks will be tackled first, including the Maymorn connection route and the Kaitoke deviation. Site access will be formed along with construction camps, with the operational base for contractors established at Maymorn.
As the Maymorn connection route and Kaitoke deviation earthworks near completion, work would commence on progressive stages of new walkway and forest road connections, commencing from the Maymorn end of the route. As each stage of walkway and forest road connection is completed and commissioned, the respective length of railway formation would be occupied and the railway built.